Happy New Year: A January Swedish/Issaquah Update

January 13, 2011 Swedish Blogger

What’s happening at Swedish Issaquah?

Happy New Year to you and yours! As we enter the mid part of the month, Swedish continues to work at an aggressive pace at the Issaquah construction site.

The exterior finish work will be complete by end of January for both the hospital wings and the medical office building, showcasing a mix of pre-cast concrete, Swiss pearl, metal panel, brick masonry and glass curtainwall.

Interior build-out continues throughout all floors ranging from paint, mechanical and electrical equipment trim, ceramic tile, ceilings and casework installation. Concurrently around the site, ground preparation for landscaping and irrigation systems continues.?

Previous Article
What Opens This July at Swedish/Issaquah?

  As a reminder, the new medical center is being opened in two stages. The first stage is the opening of ...

Next Article
Working in a Winter Wonderland: December Swedish Issaquah Update
Working in a Winter Wonderland: December Swedish Issaquah Update

Work continues at a fast pace at Swedish/Issaquah. Specifically, the crew is enclosing the building with ...